https://www.engineeringnews.co.za
Africa|Components|Contractor|Design|Efficiency|Engineering|Environment|Eskom|Generator|Generators|Health|Installation|Nuclear|Power|PROJECT|Safety|Storage|System|Water|Equipment|Maintenance
Africa|Components|Contractor|Design|Efficiency|Engineering|Environment|Eskom|Generator|Generators|Health|Installation|Nuclear|Power|PROJECT|Safety|Storage|System|Water|Equipment|Maintenance
africa|components|contractor|design|efficiency|engineering|environment|eskom|generator|generators|health|installation|nuclear|power|project|safety|storage|system|water|equipment|maintenance

Koeberg nuclear power plant steam-generator replacement project, South Africa – update

Image of Koeberg NPP

Photo by ©Creamer Media

19th July 2024

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Koeberg nuclear power plant steam-generator replacement (SGR) project.

Location
Western Cape, South Africa.

Project Owner/s
Eskom.

Project Description
The current steam generators in Unit 1 and Unit 2 at the Koeberg nuclear power station have been in operation since 1984 and 1985 respectively. The aim of the project is to extend the design life of the nuclear power station by 20 years to 2045.

The project involves the replacement of all six steam generators for units 1 and 2.

The SGR project involves the design, manufacture and installation of three steam generators in each of the Koeberg power plant's two operating units, as well as safety analyses and studies to comprehensively demonstrate the plant's design integrity, with no adverse impact on public and worker safety and health or the environment, including the enhancement of nuclear safety.

The new generators will incorporate modern design features for easy maintenance and inspections and improve heat-transfer efficiency, leading to an overall efficiency improvement of Koeberg.

The installation of the generators will be conducted during the scheduled refuelling, inspections and maintenance outages of the two units at Koeberg power station. Eskom is on track and progressing according to plan for installation during the next unit 1 and 2 outages.

The other major components of the life-extension plan include:

  • a refuelling water storage tank replacement project, completed in 2019.
  • the Unit 2 reactor pressure vessel head replacement.
  • the replacement of feed-train components on the conventional power plant, which is conducted during maintenance outages.
  • the ongoing Koeberg safety aspects of long-term operation assessment. The assessment is designed to provide the equipment-ageing management confirmation to enable the Koeberg plant to operate beyond its original life span of 40 years to at least 60 years.

Capital Expenditure
Not stated.

Planned Start/End Date
Not stated.

Latest Developments
South Africa’s National Nuclear Regulator (NNR) board has approved a 20-year life extension for Koeberg Unit 1, but has deferred a decision on the nuclear power station’s Unit 2 until late 2025, owing to an ongoing assessment of the second reactor’s safety case.

The decision, announced on July 15, came only days ahead of the July 21, 2024 expiry of Unit 1’s existing licence and effectively extended its operating life until July 21, 2044.

The licence variation is expected to be issued soon and allows for the “seamless” operation of Unit 1, as no conditions were included that required Eskom to proceed with a shutdown that had initially been scheduled to begin on July 21.

In January, the NNR also confirmed that it had agreed to Eskom’s request to separate the Unit 1 and 2 licences to align with their respective commercial operating dates, with Unit 1 having started operating in July 1984 and Unit 2 in November 1985.

For this reason, Unit 2’s existing licence will remain in place until November 9, 2025, providing the NNR board with additional time to make an assessment on the life extension of the second reactor.

Unit 2 is undergoing an extended shutdown that includes the replacement of its three steam generators, a key requirement for any long-term extension of the reactor’s operating life.

Key Contracts, Suppliers, and Consultants
Framatome (main SGR contractor); General Electric (modifications to the balance of plant or secondary turbine system); and Jacobs Engineering (balance of plant hardware changes).

Contact Details for Project Information
Eskom media desk, email mediadesk@eskom.co.za.

Edited by Creamer Media Reporter

Comments

Showroom

Universal Storage Systems (SA)
Universal Storage Systems (SA)

South African leader in Steel -Racking, -Shelving, and -Mezzanine flooring. Universal has innovated an approach which encompasses conceptualising,...

VISIT SHOWROOM 
Hanna Instruments Image
Hanna Instruments (Pty) Ltd

We supply customers with practical affordable solutions for their testing needs. Our products include benchtop, portable, in-line process control...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Economic growth a top priority for GNU
Economic growth a top priority for GNU
19th July 2024 By: Creamer Media Reporter
Magazine round up | 19 July 2024
Magazine round up | 19 July 2024
19th July 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.358 0.44s - 196pq - 2rq
Subscribe Now