https://www.engineeringnews.co.za
Construction|Energy|Environment|Flow|PROJECT|Pumps|System|Vega|Flow
Construction|Energy|Environment|Flow|PROJECT|Pumps|System|Vega|Flow
construction|energy|environment|flow-company|project|pumps|system|Vega|flow-industry-term

Galan slows construction pace at Argentina lithium brines project

12th July 2024

By: Mariaan Webb

Creamer Media Senior Deputy Editor Online

     

Font size: - +

ASX-listed Galan Lithium has opted to recalibrate its construction schedule for the Hombre Muerto West (HMW) Phase 1 project, in Argentina, citing cash preservation amid current market conditions.

The decision postpones the expected start of production from the lithium brines project to the second half of next year.

Galan has received strong international market interest in the HMW lithium concentrate. “In our view, this evidence indicates that the current lithium pricing environment and market oversupply is not expected to be a long-term trend,” MD JP Vargas de la Vega said on Friday.

Lithium inventories continue to build in the HMW Phase 1 ponds, which would provide feedstock for the HMW processing plant. It currently has an in situ inventory of 2 800 t of lithium carbonate equivalent (LCE).

“Our inventory will continue to increase as we have a low energy cost operation that only requires brine pumps to operate. As a result, once Galan finalises sales and funding arrangements, which are progressing well, the company will be in a strong position to produce a competitive low-cost lithium product,” said De la Vega.

Overall completion of the HMW Phase 1 project now sits at about 40% with the ponds system at 60% capacity. The designed ponds system can allow an inventory, until the second half of 2025, of up to 10 000 t/y LCE without the need for processing.

About 750 000 m2 of evaporation area has now been built. The current evaporation area is sufficient to produce a lithium chloride volume of about 3 000 t/y LCE. The key processing parameters, including brine well average flow rates, lithium grades and evaporation rates are all aligned with Phase 1 of the definitive feasibility study (DFS). Owing to the slower pace of construction activities, first production from HMW is now expected to be within H2 2025.

The HMW project was separated into four production phases. The initial Phase 1 DFS focuses on the production of 5 400 t/y LCE of a lithium chloride concentrate.

The Phase 2 DFS targets 21 000 t/y LCE of a lithium chloride concentrate in 2026, followed by Phase 3 production of 40 000 t/y LCE by 2028 and finally a Phase 4 production target of 60 000 t/y LCE by 2030. Phase 4 will include lithium brine sourced from both HMW and Galan’s other 100%-owned project in Argentina, Candelas.

Edited by Creamer Media Reporter

Comments

Showroom

VEGA Controls SA (Pty) Ltd
VEGA Controls SA (Pty) Ltd

For over 60 years, VEGA has provided industry-leading products for the measurement of level, density, weight and pressure. As the inventor of the...

VISIT SHOWROOM 
Rentech
Rentech

Rentech provides renewable energy products and services to the local and selected African markets. Supplying inverters, lithium and lead-acid...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine image
Magazine round up | 12 July 2024
12th July 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.405 0.491s - 192pq - 2rq
Subscribe Now