Glyn Rhonwy pumped-storage scheme project, UK
Name of the Project
Glyn Rhonwy pumped-storage scheme project.
Location
The project has been designed to bring new life to two disused slate quarries in the slopes of Cefn Du mountain in the Dyffryn Peris valley, about 1.5 km north-west of Llanberis and 11 km south-east of Caernarfon, in Wales, UK.
Client
Snowdonia Pumped Hydro.
Project Description
The project will be the first new grid-scale power storage facility built in the UK in more than 30 years. The scheme will use the Glyn Rhonwy and Chwarel Fawr slate quarries.
The 99.9 MW scheme will comprise:
• the upper reservoir at Chwarel Fawr quarry and its dam and spillway to the Nant Y Betws;
• the lower reservoir at Glyn Rhonwy quarry and its dam and spillway to Llyn Padarn;
• a penstock connecting the Chwarel Fawr quarry to the power station located adjacent to Glyn Rhonwy;
• a tailrace connecting the power station to Glyn Rhonwy; and
• the power station itself consisting of the turbines and pumps at depth with electrical distribution equipment on the surface adjacent to the power station building.
The development will be connected to the electricity distribution network through a new electrical connection. This will be exported from an on-site substation to an off-site substation near Pentir.
Jobs to Be Created
A total of 300 jobs will be created during the three-year construction and 30 full-time jobs once operational.
Value
The project will cost about £130-million to implement.
Duration
The project is expected to take three to four years to build.
Latest Developments
The project was awarded a development consent order by UK Business, Energy and Industrial Strategy Minister Greg Clark in March 2017.
Key Contracts and Suppliers
None stated.
On Budget and on Time?
Not stated.
Contact Details for Project Information
Snowdonia Pumped Hydro email info@snowdoniapumpedhydro.com.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation