Project Description
The NSW Independent Planning Commission approved the 192 MW wind farm in May 2024.

The development will comprise 32 turbines with a maximum tip height of 260 m and associated infrastructure, including a new substation and switching station required to connect to Transgrid’s existing 330 kV transmission line traversing the project site.

Potential Job Creation
The project is expected to generate 285 construction jobs and nine operational jobs.

Capital Expenditure
A$373-million.

Planned Start/End Date
Construction is expected to take about 18 to 24 months.