Sabodala-Massawa mine power plant upgrade/extension, Senegal

18th November 2022 By: Sheila Barradas - Creamer Media Research Coordinator & Senior Deputy Editor

Sabodala-Massawa mine power plant upgrade/extension, Senegal

Name of the Project
Sabodala-Massawa mine power plant upgrade/extension.

Location
Senegal.

Project Owner/s
Multinational mining company Endeavour Mining.

Project Description
The project involves an 18 MW extension to the power generating facility and upgrading the electrical and automation system of the existing power plant at the Sabodala-Massawa gold mine complex.

Potential Job Creation
Not stated.

Capital Expenditure
Not stated.

Planned Start/End Date
The project is expected to be completed and commissioned before the end of 2023.

Latest Developments
None stated.

Key Contracts, Suppliers and Consultants
Wärtsilä (engines).

Contact Details for Project Information
Endeavour Mining, tel +44 203 011 2723 or email info@endeavourmining.com.