![Hollandse Kust (west) VI Wind Farm, Netherlands](https://cisp.cachefly.net/assets/articles/images/resized/0001057983_resized_windfarmsunsetreuters1022.jpeg)
Photo by: © Reuters
Name of the Project
Hollandse Kust (west) VI Wind Farm.
Location
About 53 km from the town of Ijmuiden, in the Netherlands.
Project Owner/s
Ecowende, a joint venture between Shell and Eneco.
Project Description
The project involves the construction and operation of a wind farm with an installed capacity of about 760 MW.
The wind farm will generate enough renewable power to decarbonise about 3% of the Netherlands’ current electricity demand.
Potential Job Creation
Not stated.
Capital Expenditure
Not stated.
Planned Start/End Date
Commissioning is planned for 2026.
Latest Developments
None stated.
Key Contracts, Suppliers and Consultants
None stated.
Contact Details for Project Information
Shell Global media relations, tel +44 207 934 5550.
Eneco spokesperson Niels Stet, tel +31 6 21 33 00 26 or email niels.stet@eneco.com.