Berg gold project, Canada – update

7th June 2024 By: Sheila Barradas - Creamer Media Research Coordinator & Senior Deputy Editor

Berg gold project, Canada – update

Photo by: Surge Copper Corp

Name of the Project
Berg gold project.

Location
Tahtsa Ranges of British Columbia, Canada.

Project Owner/s
Surge Copper.

African Rainbow Minerals (ARM) entered into a subscription agreement for a private placement financing with Surge Copper in April 2024. ARM will subscribe for 39 608 708 common Surge shares for C$3.8-million through its wholly owned subsidiary ARM Copper. ARM will own 15% of Surge’s shares on completion of the placement, subject to TSX Venture Exchange and South African Reserve Bank approval.

Project Description
The project has an estimated 30-year life-of-mine. Mine planning is based on large-scale conventional drill, blast, load and haul openpit mining methods suited to the project location and local site requirements.

The process design is based on processing mineralised material from the Berg deposits through copper and molybdenum flotation to produce saleable copper and molybdenum concentrates.

Mine facilities include:

The processing plant is designed for a throughput of 90 000 t/d at 92% availability. The crushing circuit is designed with an availability of 75%. Average production is estimated at 125.9-million pounds of copper, 13.3-million pounds of molybdenum, three-million ounces of silver and 12 000 oz of gold.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
On an after-tax basis, the net present value, discounted at 8%, is estimated at C$2.1-billion and the internal rate of return at 20%, with a payback period of 3.9 years.

Capital Expenditure
About C$2-billion.

Planned Start/End Date
Not stated.

Latest Developments
Surge Copper Corp has successfully completed a $3.9-million strategic investment and has launched a metallurgical test programme for its Berg project, marking a crucial step towards the prefeasibility study. 

The test, conducted by ALS Metallurgy Kamloops, will refine flowsheet design parameters over a six-month period using samples from recent drill cores. With this funding and testwork under way, project development is expected to advance.

Key Contracts, Suppliers and Consultants
ALS Metallurgy Kamloops (metallurgical test programme).

Contact Details for Project Information
Surge Copper, tel +1 604 718 5454 or email info@surgecopper.com.