Name of the Project
Baltica offshore wind project.
Location
About 40 km from the northern coast of Poland, between Łeba and Ustka.
Project Owner/s
PGE Group and Ørsted.
Project Description
The project, with a total capacity of about 2.5 GW, consists of Baltica 2, with a capacity of about 1.5 GW and one-hundred-and-seven 14 MW wind turbines.
Once operational, the project will avoid more than 5.4-million tons of CO2 emissions a year, or the equivalent emissions from about 3.6-million diesel cars. It will also provide electricity for about 2.4-million homes in Poland.
Baltica 3 will have a capacity of about 1 GW.
Potential Job Creation
Not stated.
Capital Expenditure
The European Investment Bank (EIB) approved the in-principle financing of the Baltica project to €1.4-billion in August 2023.
Planned Start/End Date
Baltica 2 is scheduled to be commissioned in 2027 and Baltica 3 by the end of this decade.
Latest Developments
None stated.
Key Contracts, Suppliers and Consultants
None stated.
Contact Details for Project Information
PGE Group, tel +48 22 340 11 77.
Ørsted, tel +45 99 55 11 11 or email info@orsted.com