B2Gold unveils new PEA for ‘medium-scale’ Gramalote project

19th June 2024

By: Mariaan Webb

Creamer Media Senior Deputy Editor Online

     

Font size: - +

Vancouver-headquartered B2Gold has unveiled a new preliminary economic assessment (PEA) for the Gramalote project, in Colombia, outlining a medium-scale operation that marks a shift from previous plans.

The new PEA envisions an openpit mine producing an average of 185 000 oz/y of gold over a 12.5-year lifespan. In the initial five years, the mine is expected to yield 234 000 oz/y at an all-in sustaining cost of $822/oz.

The Gramalote project, which was previously a joint venture with AngloGold Ashanti, is now solely owned by B2Gold following AngloGold’s exit in September last year. The departure came after an optimised feasibility study for a larger-scale operation did not meet AngloGold’s expectations.

B2Gold’s revised plan includes a 16 500 t/d processing plant, capable of handling up to six-million tonnes a year.

The project's preproduction capital requirement is estimated at $807-million, with an additional $364-million in sustaining capital over its life.

Financially, the PEA is based on a gold price of $2 200/oz for the first three years and a long-term price of $2 000/oz. Under these assumptions, the project has an aftertax net present value of $778-million and an internal rate of return of 20.6%, with a payback of 3.1 years.

The mineral resource estimate for the project that forms the basis for the PEA includes indicated mineral resources of 192.2-million tonnes grading 0.68 g/t gold for a total of 4.21-million ounces of gold and inferred mineral resources of 85.4-million tonnes grading 0.54 g/t gold for a total of 1.48-million ounces.

Following a positive PEA, B2Gold will progress to a feasibility study, targeted for completion by the middle of next year.

Owing to the work completed for previous studies, the work remaining to finalise a feasibility study for the updated medium-scale project is not extensive. The main work programme for the feasibility study includes geotechnical and environmental site investigations for the processing plant and waste dump footprints, as well as capital and operating cost estimates.

Owing to the desired modifications to the processing plant and infrastructure locations, a modified environment impact study (EIS) is required. B2Gold has started work on the modifications to the EIS and expects it to be completed and submitted shortly following the completion of the feasibility study.

Edited by Creamer Media Reporter

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION